Option Construction cost
(million)
Crash reduction benefit
(million)
Travel time disbenefits
(million)
Annual death and serious injury crashes avoided Benefit cost ratio
1a: Variable at schools $9.1 $5.2 $4.1 0.3 0.1
1b: Variable at schools (accelerated) $10.4 $6.2 $4.9 0.3 0.1
2a: Permanent at schools $6.5 $91.8 $21.3 6.2 10.9
2b: Permanent at schools (accelerated) $7.4 $103.7 $25.5 6.2 10.6
3: 40 km/h default $12.5 $181.5 $287.0 10.7 -8.4
4: 30 km/h default $26.2 $193.1 $366.0 11.2 -6.6
5a: 40 km/h default + variable at schools $14.6 $175.4 $237.0 10.8 -6.3
5b: 40 km/h default + variable at schools (accelerated) $16.1 $149.6 $277.0 10.8 -5.9
6: 40/30 km/h mix $26.2 $278.1 $327.0 16.3 -1.8